Building For Change Project

Year Execution: 
2021
Country: 
Belice
Organization in Charge: 
Hand In Hand Ministries
USD: 
28.000
Nº of Families helped: 
20
Zone: 
Rural

 

To begin with, SELAVIP funding for project to begin January 2021 was not received until March 2021 due to wiring challenges, however, the NGO continued building as they have established very good working relationships with their creditors. Other issues they have encountered are current gathering restrictions, which forces our homes to be built in more days than normal (9 instead of 4 days), securing lumber and other material availability due to shortages in the country, rising costs in materials, securing more volunteers, resource limitations (work truck break down). Proximity of building has been extended to outskirt district due to lack of land availability in city and rural areas, and the needs of families.