Construction Pilote Des Habitats Par Famille Pou

Year Execution: 
2021
Country: 
Congo (Kinshasa)
Organization in Charge: 
Aide à l’Enfance
USD: 
29.000
Nº of Families helped: 
29
Zone: 
Rural

 

The first step of the project launched on March 1, 2021 consisted of carrying out the masonry work up to the expectation level of the roof, that is to say after the chaining.
This 1st stage of the project made it possible to build 15 houses whose masonry work is finished, and 4 other houses whose masonry work will be completed in 10 days, for a total of 19 houses totally finished at masonry level in as part of the first stage of the project.

The second stage of the project consisted of sheet metal the 20 houses whose masonry work came to an end during the first period of the launch of the project, and then to build 5 new houses bedroom + living room, the current work of which is at window level because of the delay known in the shortage of cement in Brazzaville following the technical maintenance works of the railway which lasted a month, systematically preventing Brazzaville from the circulation of the freight trains.

The masonry work which was delayed on the 5 houses is proceeding normally and will be completed.