Settlements Development Of Yao Villas Community
Year Execution:
2021Country:
FilipinasOrganization in Charge:
Foundation For The Development Of The Urban PoorUSD:
33.600Nº of Families helped:
24Zone:
Rural
On the status of the project implementation: the NGO has experienced delays because of the lockdown they recently had in Metro Manila and the surrounding provinces due to increasing cases of COVID.
Mobilization work done in the 8 lots is mostly clearing of structures to include trees.
This is the latest schedule as set with the community association:
· Boundary Survey schedule of Engineer Star - 13 September 2021.
· Posting of order of materials - 13 September 2021.
· Expected delivery of construction materials - 14 September 2021.
· Expected start of construction for the first batch of 8 recipients - 14 - 15 September 2021.