Settlements Development Of Yao Villas Community

Year Execution: 
2021
Country: 
Filipinas
Organization in Charge: 
Foundation For The Development Of The Urban Poor
USD: 
33.600
Nº of Families helped: 
24
Zone: 
Rural

 

On the status of the project implementation: the NGO has experienced delays because of the lockdown they recently had in Metro Manila and the surrounding provinces due to increasing cases of COVID.

Mobilization work done in the 8 lots is mostly clearing of structures to include trees.

This is the latest schedule as set with the community association:
· Boundary Survey schedule of Engineer Star - 13 September 2021.
· Posting of order of materials - 13 September 2021.
· Expected delivery of construction materials - 14 September 2021.
· Expected start of construction for the first batch of 8 recipients - 14 - 15 September 2021.