Basic and Affordable Shelter for poor community

Año Ejecución: 
2020
País: 
Bangladesh
Organización responsable: 
DHARA
USD: 
72,000
Nº de familias atendidas: 
60
Zona: 
Urban

The beneficiaries are 60 families in Jashore and in Shyamnager. The project’s execution has involved the following activities : land preparation: it started with the help of SIC leaders and the beneficiaries to ready the land where the new housing is being built, materials Distribution occurs according to the SELAVIP’s instalment, first 25 % corresponding to sand, bricks, cement etc.after. The transportation process is handled by the suppliers. At present average 75-80% of total construction works completed.Also , the construction works continuing to follow the designer of the project. Supervision & monitoring: Under this project, supervision and monitoring system is the continuing process from the beginning to after end of the project and the staffs of the project always supervise and monitoring the project activities.